I have a project with tasks, start and end dates, etc. I want to reschedule everything forward 3 months.
I followed the instructions found in help
>>Adjust Dates
If you use another project file as a template for a new project, you can use the Adjust Dates macro to schedule this project with the right start and finish dates for tasks.
The Adjust Dates macro helps you adjust all dates in your project in relation to a new start date that you provide when prompted. Tasks with constraints are also adjusted.
To run the Adjust Dates macro, click Adjust Dates<<
My dates are now all in the year 2010 range. I suspect what happened is, the person who created this file had a default start date of 1/1/01, but entered actual task dates in the task list. How do I straighten this out easily?