    Can anyone tell me why the finish date of the Project Summary Task might be earlier than one of the project tasks? It seems to me it shouldn’t be possible.

    Viewing 1 reply thread
    Author
    Replies
    • #833475

      Bryan,

      This could happen if you are looking at the Baseline Finish Dates and someone updated a part of the baseline. Is the finish date you are referring to the Planned Finish, Baseline Finish, or Actual Finish? Text field?

      Also – any chance you have a task inserted from another project?

    • #833476

      Bryan,

      This could happen if you are looking at the Baseline Finish Dates and someone updated a part of the baseline. Is the finish date you are referring to the Planned Finish, Baseline Finish, or Actual Finish? Text field?

      Also – any chance you have a task inserted from another project?

      • #833634

        Oh you’ll just love this. I’m just looking at the project summary task finish date, but somehow it was just displaying day/month and it’s going to 2005! 80 hour weeks does this to one I guess. Thanks again.

        • #834063

          … it happens to all of us. Hopefully, you can lessen your workload to less then 80 hours per week. cheers

          • #834068

            No kidding! I feel like I’ve been losing brain cells daily. BTW, I’m naminig you the good luck guy. Right after I read your post one of my projects was put on hold, so I get to take off today after lunch cheers

            • #834125

              … well then you should read my posts every day, but sorry to say, I don’t post as much as the others.

              Have a great weekend.

            • #835426

              But it is QUALITY not QUANTITY that counts![thumbsup]

            • #835634

              Thanks Catherine. However, that assumes that the quantity of my posts do contain some quality – which is not always the case.

              … unless of course you are a stack of money, then I will take quantity over quality. laugh

            • #835635

              Thanks Catherine. However, that assumes that the quantity of my posts do contain some quality – which is not always the case.

              … unless of course you are a stack of money, then I will take quantity over quality. laugh

            • #835427

              But it is QUALITY not QUANTITY that counts![thumbsup]

            • #834126

              … well then you should read my posts every day, but sorry to say, I don’t post as much as the others.

              Have a great weekend.

          • #834069

            No kidding! I feel like I’ve been losing brain cells daily. BTW, I’m naminig you the good luck guy. Right after I read your post one of my projects was put on hold, so I get to take off today after lunch cheers

        • #834064

          … it happens to all of us. Hopefully, you can lessen your workload to less then 80 hours per week. cheers

      • #833635

        Oh you’ll just love this. I’m just looking at the project summary task finish date, but somehow it was just displaying day/month and it’s going to 2005! 80 hour weeks does this to one I guess. Thanks again.

    Viewing 1 reply thread
    Reply To: Reply #833475 in Finish dates don’t jive (2003)

    You can use BBCodes to format your content.
    Your account can't use all available BBCodes, they will be stripped before saving.

    Your information:




    Cancel