Hi,
I have a Project file of about 300 tasks, with task dates starting in September. I want to import this into another “master project file”, which contains about 1000 tasks. The “master project file” is a project which started in June. So, when I import the 300-task project into the master file, it shifts all of the dates to the June start date. All of them are changed – and they’re all wrong.
I guess it does this because the tasks are all defined as Start “as soon as possible”.
How do I import this project and force the dates to stay the same? (Or, at a minimum, the dates which have no dependencies but are shown as starting in September).
Thanks
PaulaG