    Hi,
    I have a Project file of about 300 tasks, with task dates starting in September. I want to import this into another “master project file”, which contains about 1000 tasks. The “master project file” is a project which started in June. So, when I import the 300-task project into the master file, it shifts all of the dates to the June start date. All of them are changed – and they’re all wrong.
    I guess it does this because the tasks are all defined as Start “as soon as possible”.

    How do I import this project and force the dates to stay the same? (Or, at a minimum, the dates which have no dependencies but are shown as starting in September).

    Thanks
    PaulaG

    Viewing 1 reply thread
    Author
    Replies
    • #726897

      Did you try setting the first date of the imported project that drives all other dates as a must start on constraint prior to importing it?

      • #726973

        Yes, I did this and it worked for all tasks which didn’t have predecessors. Other tasks still moved to the wrong start date.

        In the end, I had to set a “must start on” constraint on the 1st task, then set a “start no sooner than” constraint on all of the other tasks which did not have predecessors. A bit of a pain, but it worked.
        Thanks
        PaulaG

      • #726974

        Yes, I did this and it worked for all tasks which didn’t have predecessors. Other tasks still moved to the wrong start date.

        In the end, I had to set a “must start on” constraint on the 1st task, then set a “start no sooner than” constraint on all of the other tasks which did not have predecessors. A bit of a pain, but it worked.
        Thanks
        PaulaG

    • #726898

      Did you try setting the first date of the imported project that drives all other dates as a must start on constraint prior to importing it?

    Viewing 1 reply thread
    Reply To: Reply #726897 in Importing tasks with correct dates (2002)

    You can use BBCodes to format your content.
    Your account can't use all available BBCodes, they will be stripped before saving.

    Your information:




    Cancel