Hi,
I am trying to set up a project using resource tracking, typically I setup project using Duration and normally do not worry about resource levelling, but now I need to.
Basically I want to do the following.
1) Define a Task with 3 sub tasks
2) Assign one or more resources to that sub task with a fixed number of days each
3) Level the plan so that I can see the where the constraints are.
eg
Task 1 30 days
Sub Task 1 – Resource 1 – 10 Days, Resource 2 – 10 Days, Resource 3 – 2 days
Sub Task 2 – Resource 1 – 10 Days
Sub Task 3 – Resource 3 – 10 Days
All Tasks are linked but resources in sub task 1 can work in parallel.
I cannot find in MS Project how I can do this. I have messed about with resource allocation in % but once I level the duration becomes all messed up. I can enter the days in the resource usage sheet but this is by resource and not task so makes it difficult to work at task level.
Any guidance please.
Regards
Mike