    How do I remove the date that automatically shows up next to a milestone in MS Project 2010. I haven’t used this program much, and I’m just lost. Thanks!

    Viewing 0 reply threads
    Author
    Replies
    • #1409982

      Select the milestone in the TaskName column (Task tab selected on the ribbon): Then click on Information in the ribbon to pull up the Task Information view. Under dates, delete the dates in the Start: and Finish: fields. click OK The date will no-longer be visible next to the milestone. (Although, I must add that the purpose of a milestone is to know whether or not the milestone has been reached (or will be reached) on the desire4d day(date), so I always want the date to be visible. I hope this helps?

      (You can also double-click the milestone to view the Task Information window for that milestone: Then the same applies: Select and delete the start and finish dates and click on OK)

      (You can also do this by right-clicking in the start and finish cells of the respective columns for the milestone and selecting “clear contents”)

      My Rig: AMD Ryzen 9 5900X 12-Core CPU; ASUS Cross Hair VIII Formula Mobo; Win 11 Pro (64 bit)-(UEFI-booted); 32GB RAM; 2TB Corsair Force Series MP600 Pro 2TB PCIe Gen 4.0 M.2 NVMe SSD. 1TB SAMSUNG 960 EVO M.2 NVME SSD; MSI GeForce RTX 3090 VENTUS 3X 24G OC; Microsoft 365 Home; Condusiv SSDKeeper Professional; Acronis Cyberprotect, VMWare Workstation Pro V17.5. HP 1TB USB SSD External Backup Drive). Dell G-Sync G3223Q 144Hz Monitor.

    Viewing 0 reply threads
    Reply To: MS Project 2010: Removing date from milestones

    You can use BBCodes to format your content.
    Your account can't use all available BBCodes, they will be stripped before saving.

    Your information: