    I have a simple task list with a set of deliverables at the bottom. Each deliverable is due right one of the above sections. I’d like to NOT set them to be due on a date so if the tasks change, it changes, without being wrong. All tasks are ASAP and few constraints.

    Tasks
    Task 1 Set
    Task 2 Set
    Task 3 Set
    Deliverables
    Deliverable 1 should level to be done right when Task 1 Set is complete. It has Task 1 set as a Predecessor.
    Deliverable 2 etc.

    Right now they level to show up starting after Task 3 Set.

    Help!

    Viewing 0 reply threads
    Author
    Replies
    • #1186584

      What other Predecessors have you set? Are there any Summary-level tasks (e.g., Tasks, Deliverables, etc…)? Is there a Predecessor for the summary-level task? Other than the Predecessor for Deliverable 1, what Predecessors have you set?

      • #1186601

        Sorry to say that project is long gone and I don’t exactly remember the details. Thanks for the reply.

        What other Predecessors have you set? Are there any Summary-level tasks (e.g., Tasks, Deliverables, etc…)? Is there a Predecessor for the summary-level task? Other than the Predecessor for Deliverable 1, what Predecessors have you set?

    Viewing 0 reply threads
    Reply To: MSP07 Scheduling issue

    You can use BBCodes to format your content.
    Your account can't use all available BBCodes, they will be stripped before saving.

    Your information: