I have a simple task list with a set of deliverables at the bottom. Each deliverable is due right one of the above sections. I’d like to NOT set them to be due on a date so if the tasks change, it changes, without being wrong. All tasks are ASAP and few constraints.
Tasks
Task 1 Set
Task 2 Set
Task 3 Set
Deliverables
Deliverable 1 should level to be done right when Task 1 Set is complete. It has Task 1 set as a Predecessor.
Deliverable 2 etc.
Right now they level to show up starting after Task 3 Set.
Help!