I have added the Project Summary Task from Options and have not entered some actuals. However the summary actual duration days are far less than the true actual duration totals (they follow on FS so it is nothing to do with overlapping tasks).
Is there anything I should know about the way project calculates the project summary figures?
(the summary report also shows the total actual as being the amount shown in the summary task rather than the actual total duration taking the start date of the first completed task and the end date of the last completed task)
Thanks
Roberta