I’ve a task with multiple resourses. One of them shows 200% in units. I try
to change to 100% and it changes it back. I can’t seem to change anything
that will allow me to change that. Help? I know it’s just a combo of effort driven, type, etc. But can’t make it work!
On that same note, how can I tell project to NEVER use anything but 100%.
These are all people and can only be <= 100%.