• resourses across multiple projects (Project 2000)

    Home » Forums » AskWoody support » Productivity software by function » Other MS apps » resourses across multiple projects (Project 2000)

    Author
    Topic
    #435451

    I have several staff and multiple projects running concurrently. Each staff member has a role/task to perform on the different projects but of course one project doesn’t end to free up that staff members time, so they can then go to the other, i need each staff member to swap from project to project depending on what skill is required on any given project at any time. this way alleviating downtime for any particular staff member. Basically i want to utilise resources across live projects? Can any one direct me on how to do this please?

    Webmistress!

    Viewing 0 reply threads
    Author
    Replies
    • #1029247

      You could create a shared resource pool to view resource allocations accross multiple projects. Here are the basic steps
      Create a plan called Resource Pool as a file dedicated to storing your resources and add your available resources to the resource entry table
      Open the Sharer file and select Tools, Resource Sharing, Share Resources — this will bring in and make available the resources in the pool file.
      I would recommend using a dedicated file for storing your resources. If you have resources in the sharer files they consolidate into one single resource list. It is easier to manage with a dedicated file.

      Carla

      • #1062716

        After trying different solutions, I think this is the best for showing assignments across several project. Thanks

    Viewing 0 reply threads
    Reply To: Reply #1029247 in resourses across multiple projects (Project 2000)

    You can use BBCodes to format your content.
    Your account can't use all available BBCodes, they will be stripped before saving.

    Your information:




    Cancel