    ok so im completely new to this app, so i have 6 tasks/projects/todos

    your goal is to find out which you should be working on first to finish everything in the least days

    is there a feature to easily do this? if ms project 2013 can’t do this, you can recommend anything else

    task1 takes 1 day
    task2 takes 2 days
    task3 takes 3 days requres both task1 and task2
    task4 takes 2 days and requires task 1
    task5 takes 1 day and requires task 3 and 4
    task6 takse 6 days and requres task 2