(Edited by bdesilva on 12-May-04 12:39. )
I’ve inherited a project that the previous owner entered all the start and finish dates. I like to use dependencies and resources to drive those dates. How do I firstly identify all the hand entered dates, and then remove them so Project manages them, or will that just happen based on my dependencies.
I should add that I’ve changed most of the contraints to ASAP so I ‘think’ I’ve taken care of this. I’m just not certain