I have a project that is slipping. What is the best way to show reality in the project? Example
Task 1 Start = 4/10 Finish = 5/13. 50% complete
As of today, 5/11, clearly it’s not going to make it. The best case is now probably closer to the end of the month. I’d like MSP to take into consideration the % complete and recalculate the finish date.
Task 2 Start = 5/1 Finish = 5/13. 0% complete
This should change to best case start = 5/11.
I’ve tried the Adjust Dates button, but am not certain it handles this well. It mentions adjusting the Project START, which also seems wrong for what I want.